Client:
Leighton Contractors
Scope:
Topsoil and overburden pre-strip
Location:
Moranbah, QLD
Project Features:
MCG is currently engaged in the pre-strip of topsoil and overburden material for Leighton Contractors at the green fields Poitrel mine site. The excavation involves around 2,400,000bcm with scraper and bulldozer teams carrying out work on two fronts to ensure the timely completion and handover of works for the overburden excavation to start. Activities on site also include drainage and infrastructure works.]